Formula and worked example
Allowance-adjusted finished volume = finished target × (1 + allowance ÷ 100). Combined loose ingredient volume = allowance-adjusted finished volume × stated finished-to-loose factor. Each ingredient’s loose volume = combined loose volume × its part ÷ sum of all three parts.
Arithmetic example: 1 yd³ equals 27 ft³. At an editable 5% allowance, the finished quantity is 28.35 ft³. With an entered factor of 1.5, combined loose ingredients total 42.525 ft³ or 1.575 yd³. A 1:2:3 loose-volume proportion has six total parts: cement is 7.0875 ft³, sand 14.175 ft³ and coarse aggregate 21.2625 ft³. The factor, proportions and allowance are examples, not an approved mix or recommended yield assumption.
Finished concrete and loose ingredients are different quantities
The factor is an explicit assumption converting the finished-volume requirement into a combined loose ingredient requirement. It is not inferred from the ratio or treated as a universal physical constant. Use a factor verified for the actual materials and method with the responsible project team. Do not apply it again to ingredient quantities already converted to loose volume.
Loose volumes include material packing and voids; their sum is not a measured fresh-concrete yield. This nominal volume method does not establish a concrete mixture’s performance or suitability. Water, aggregate moisture and bulking, absorption, admixtures, handling and specification requirements must be addressed separately by the approved mix process.
Volume proportions and allowance
Parts are relative loose volumes, not weight ratios. Multiplying all parts by the same positive number preserves the result: 1:2:3 and 2:4:6 have identical shares. Unlike the separate Concrete Mix batch page, these entries do not define one mixer batch or a container size. All three parts must be positive for this concrete constituent method.
Allowance is applied once to finished volume before the factor and shares. The result shows each material’s base loose volume and its additional allowance volume. If the source finished quantity already includes the desired allowance, enter 0%. No whole-batch, bag, pallet or delivery rounding is performed.
Optional masses from supplied loose bulk densities
Each ingredient mass = its allowance-adjusted loose volume × that ingredient’s supplied loose bulk density. Enter all three densities to enable weights. No automatic cement, sand or aggregate density is provided. Use source data matching the loose material, grading, moisture and measurement condition represented by the volume assumption.
Do not enter particle specific gravity, compacted bulk density or finished-concrete density as loose bulk density. The sum of the three estimated masses excludes water and other unentered ingredients; it is not a finished-concrete mass. The page does not infer cement-bag count or packaging.
Arithmetic US example: for the default loose volumes, user-entered densities of 94 lb/ft³ for cement and 100 lb/ft³ for both sand and aggregate produce 666.225 lb cement, 1417.5 lb sand and 2126.25 lb aggregate. Their sum is 4209.975 lb. These densities illustrate multiplication only and are not recommended material properties.
Independent metric reference
For a 1 m³ finished target, 10% allowance and entered factor 1.5, the combined loose requirement is 1.65 m³. At 1:2:3, cement is 0.275 m³, sand 0.55 m³ and aggregate 0.825 m³. Their pre-allowance loose volumes are 0.25, 0.5 and 0.75 m³ respectively.
Using illustrative supplied densities of 1440, 1600 and 1500 kg/m³ respectively gives 396 kg cement, 880 kg sand and 1237.5 kg aggregate, totaling 2513.5 kg. These densities are arithmetic inputs, not specifications. Unit conversion is applied before multiplication.
Units, precision and limits
Finished volume accepts yd³, ft³ or m³; density accepts lb/ft³ or kg/m³. Selectors retain their numeric entries, so match each input to its source. One yd³ equals exactly 27 ft³ or 0.764554857984 m³; one lb equals 0.45359237 kg. Exact reduced fractions preserve decimal proportions and conversions before display rounding to three decimals. Rounded displayed constituent values may not sum exactly to the displayed total.
Target volume must be positive and no greater than 1 million m³. Allowance accepts 0–100%; the stated factor accepts 1–3 as an input check, not a recommended factor range. Parts must be positive and no greater than 1 million each. Optional loose densities must be 1–10000 kg/m³ after conversion. Decimal entries accept up to 18 places. These limits do not establish physical suitability.
Scope and related calculations
This is a bulk constituent takeoff using explicit nominal volume assumptions. It does not select structural mix proportions, water dose, moisture corrections, strength or supplier ordering rules. Use the separate Cement Calculator for cement-only mass and bags, and Concrete Mix for scaling a declared batch with its verified finished yield. Ratio normalization remains a separate requested calculator page.
Reference
NRMCA CIP 8: Discrepancies in Yield distinguishes fresh-concrete batch yield and its verification from material quantities. Civilable does not claim that loose ingredient sums establish fresh yield; the finished-to-loose factor remains an explicit project assumption, with no universal factor or approved mix inferred from the source.