Concrete footing quantity takeoff
Enter the concrete dimensions from your footing schedule. Use separate groups for different footing sizes or types, and enter the number of identical runs or footings in each group. Results include a per-group breakdown and a combined allowance.
Footing volume formulas
Strip footing: net run length × constant width × concrete thickness × identical runs. Rectangular isolated footing: length × width × thickness × identical footings. Circular isolated footing: π × diameter² / 4 × thickness × identical footings.
Add the group volumes to get the base quantity. Total with allowance = base × (1 + allowance / 100). Use the concrete thickness, rather than the total excavation depth or depth below ground.
Worked example: strip plus isolated footings
A 40 ft net strip run, 24 in wide and 12 in thick, contains 40 × 2 × 1 = 80 ft³. Four isolated footings, each 4 ft × 4 ft × 12 in, add 4 × 16 = 64 ft³. Base volume is 144 ft³. A 5% allowance adds 7.2 ft³, giving 151.2 ft³ = 5.6 yd³ = 4.282 m³.
Count strip intersections once
Lengths must describe non-overlapping concrete. For a rectangular footing ring with an outside footprint of 20 ft × 12 ft and a uniform 2 ft width, count the two 20 ft strips plus two clear 8 ft strips: net length = 56 ft. At 1 ft thickness, the volume is 56 × 2 × 1 = 112 ft³. Using the full outside perimeter of 64 ft with the same width would count the corners twice.
For branches or varying widths, split the plan into non-overlapping rectangles. The calculator sums your entries; it cannot inspect the plan or automatically remove intersections. If you enter one combined net length for several identical runs, use quantity 1 to avoid multiplying those runs again.
Use groups for repeated footings
One group can represent several identical isolated footings. Use another group when the length, width, diameter or thickness changes. Circular isolated footings are modeled as solid cylinders of constant diameter. Break stepped footings into separate non-overlapping blocks; tapered or sloped shapes require a separate takeoff.
Units, allowance and ordering
Each dimension has its own unit selector. Choosing a new unit converts the entered value. The feet/inches and metric buttons convert every group's dimensions. Cubic yards = cubic feet / 27; cubic meters = cubic feet × 0.028316846592.
The 5% allowance is an editable example. Confirm site losses, excavation variation, overbreak and delivery increments with your project team and concrete supplier. Results use unrounded measurements; displayed volumes are rounded to three decimals.
Use the approved footing dimensions
This calculator estimates concrete from supplied dimensions. Footing width, thickness, reinforcement, founding depth and soil bearing requirements come from the project design. Stem walls, columns and pedestals above the footing are separate concrete items; include only the footing bodies here.
References